Confirming Planned Workstep Dates

The Workstep Planned Start and Finish Dates window allows you to confirm and edit the planned workstep dates that are inherited from the template.

The dates that display on this window are calculated based on date calculation conditions set in the template. All dates can be overridden.

Conditions Used Result

Full calculation method

Dates are calculated from template rules

Dates are calculated for the fiscal year end (FYE) for the workstep based on the rule calculation.

Direct entry method

No dates entered for the template

Dates are blank. It is recommended that you enter the dates, but this is not required.

Full calculation method

Basis not selected from the template

Dates are blank. It is recommended that you enter the dates, but this is not required.

Dates are dependent on other data (for example, the actual start date)

Other data is not yet available

Dates are blank.

This window is displayed by clicking Confirm planned workstep dates on the New Project - Other Information window. For an overview, see Managing Projects.