Managing Project Budget and Actual Amounts
In the project profile, you can manage budget amounts, actual amounts, and variances. Both the budget calculation method and budget amounts can be adjusted.
Variances are reported in dollar amounts and percentages. Hours, amounts, costs, and expenses are presented in summary. Summarized amounts can be expanded to display the individual workstep amounts that make up the summarized totals.
To examine or edit budgeted and actual amounts, do the following:
- Open the project profile.
- Click Budget and Financial > Budget to Actual on the navigation panel.
- If you want to display cost, gross profit, and net profit in the budget summary, select Track cost and profit in addition to billings.
- Do one of the following depending on how the budget should be created:
- Enter budget amounts manually.
- Build a budget based on the workstep amounts. This option is only available if worksteps are included in the template.
- Enter an expected realization percentage rate.
- Click one of the Save buttons or Cancel.