Managing Workstep Statuses in a Project Template
                                                    The Status section is where you can select the status that should be assigned to a project when a workstep is marked complete. To manage workstep statuses, do the following:
Open the Templates list.		
            - Select a project template, and then click
. You can also right-click and select Open from the menu. - Click Worksteps on the navigation panel. The window displays a grid listing the worksteps in the project template.
 - Select the workstep you want to edit.
 - If the workstep detail tabs do not display at the bottom of the window, click Show Details to display them at the bottom of the window.
 - Click the Status tab.
 - Click the blue link to open the Select status window.
 - Select the project status that should be applied when this workstep is completed.
 - Click OK.
 - Click one of the 
Save buttons or Cancel.
     